Thursday, March 25, 2010
Project RACI
The projects where this tool has been used and well understood by the project team, there have been fewer gotchas in terms of 'who does what and why'. Project manager can harvest the benefits of this tool throughout the project
Wednesday, February 24, 2010
Great project plans do not assure accurate project status reports
It has been observed, on multiple occasions that as the project activities start happening, the updates to a project plan starts to fall behind. Some tasks are updated with % complete, however, actual start and finish dates are not updated. If the project manager is has not set his team’s expectations about requiring an update about progress of their respective tasks from them, he may get updates from some but not all. Thus the project plan update is incomplete and inaccurate. Also, if a project is 50% complete, doesn’t always mean that the remaining 50% will take twice the time already expended.
Creating and maintaining a project plan requires discipline. The project manager should set aside time each week to make those updates. Otherwise, the updates are often not made at all or made in an ad-hoc manner. The updates should include % complete and updates to actual start and finish date fields. In case the finish date is likely to be pushed out, the project manager should make that update.
Tuesday, February 2, 2010
knowledge harvesting is so hard!
One of the reasons is that people believe that documentation needs to be done at the end. As the project nears completion so much has transpired and documentation during the course of the project is in emails, in post-it notes, and people's brains that it is impossible to convert that into documentation that is coherent and meaningful. As a result, even if sufficient time is allocated at the end of the project to complete documentation, the documentation that is created is incomplete, lacks context (why certain things were done) and becomes merely an academic exercise
The consequence of incomplete and insufficient documentation is that the product or service created as a result of the project is not easily maintainable thereby increasing the total cost of ownership (TCO).
Project manager can take some simple steps to circumvent this problem:
1) Take bite-sized-documentation approach - document things as they happen without having to re-write. Provide a control mechanism to measure whether this approach is working and that the documentation is leverageable.
2) Do not take a one-size-fits-all approach - depending on type of project and its duration, different types of documentation may be necessary. Being pragmatic will ensure good documentation and team members will be more willing to complete documentation
3) Always use a central repository to store documentation - sharepoint, project wiki, etc. are good options. This eliminates the need to have to bring it all together towards the end of the project
Saturday, December 12, 2009
It cannot happen on my project....
On a business critical project where the organization did not have any prior experience implementing new software, a common sense approach should have been to have the software vendor accountable for implementation. However, when few initial milestones (provided by software vendor) were missed, it was assumed that the end date will be met through super-human efforts. This was a folly that resulted in additional milestones being missed and as expected dented confidence of end-user community in the project itself. At this point, project sponsor challenged the project management group (including the software vendor leadership) to re-baseline the project and build a closed-loop control mechanism to always keep the project on-track. The control mechanism (comprising of exception reports, clear metrics definition, etc.) should alert senior management in case of abnormal situations.